For Tech Support, Custom Projects and Pricing
Toll Free 1-866-536-5506
 
 

 

Hatch Rail - 3 Part Specification

Download 3 Part Specifications [MS Word]

Download 3 Part Specifications [PDF]

3 PART SPECIFICATION: PART 1

GENERAL 1.01 SECTION INCLUDES:
A. The work of this section consists of the furnishing of all labor, equipment, materials and devices required in conjunction with the installation of RoofTop Hatch Rail.
B. Manufacturer must supply a letter from the roofing manufacturer that the system to be installed will not void the roof warranty.

1.02 RELATED SECTIONS:
A. Division 5 – Metals Section
B. Division 7 – Roofing Division
C. Division 10 – Safety Equipment

1.03 REFERENCES:
A. American Society for Testing and Materials (ASTM):
1. A 123-89a Zinc (Hot-Dip Galvanized) Coating on Iron and Steel Products.
2. A 153-82 Zinc Coating (Hot-Dip) Steel and Iron Hardware.
3. A 167-92b Stainless and Heat-Resisting Chromium-Nickel Steel Plate, Sheet and Plate.
4. A 570-92 Steel, Sheet and Strip, Carbon, Hot-Rolled, Structural Quality.
5. G23-88 Plastic UV Aging.
B. The Occupational Safety and Health Administration (OSHA) Standards1. OSHA regulation Title 29 of 1910.232. OSHA regulation Title 29 of 1910.27
C. National Roofing Contractors Association (NRCA): NRCA Roofing and Waterproofing Manual, current edition.
D. Sheet Metal and Air Conditioning Contractor's Association, Inc. (SMACNA): Architectural Sheet Metal Manual, current edition.

1.04 SUBMITTALS:
A. Product Data: Submit manufacturer's product data sheets. Including installation instructions for each fabricated unit.
B. Manufacturer must meet requirements under section 1910.23 and 1910.27 of OSHA Standards.
C. Contractor must supply a letter from the roofing manufacturer that the system to be installed will not void the roof warranty.

1.05 QUALITY CONTROL:
A. The Contractor or his representative on request will inspect the completed installation and report in writing that the design requirements meet with the Manufacture's requirements.

1.06 WARRANTY:
A. The Product Manufacturer shall provide a full system material warranty necessary to cover all cost of repairs and/ or replacement of all components of the system against defects in manufacturing for the period of seven years. Warranty will include Acts of God, vandalism, neglect, metal finish or improper installation.

 

Part 2 – PRODUCTS:
2.01 MANUFACTURER:
A. The RoofTop Hatch Safety Guard-Rail system shall be manufactured by RoofTop Accessories P.O. Box 1671 Tomball, Texas 77377 phone 866.536.5506 fax 281.516.9002 www.rooftopaccessories.com

2.02 MATERIALS:
A. Pipe: 1 5/8" OD A53 Grade B seamed steel.
B. Safety Finish: Safety yellow powder coated.
C. Chain: Zinc plated 3/16" ASTM proof coil with hoop and rings as required.
D. Accessories: Zinc plated threaded rods, caps, nuts, bolts and washers.
E. Railing Camps: Welded in place u clamp with allen screw or as required.

2.03 RELATED PRODUCTS:
A. Compression Gasket 3/4" Dow Chemical Co. Styrofoam

2.04 MODELS:
A. Models:                      Net Opening
1. HR3232                   24” x 24”
2. HR3238                  24” x 30”
3. HR3244                  24” x 36”
4. HR3838                   30” x 30”
5. HR3844                   30” x 36”
6. HR4444                   36” x 36”
7. HR4456                   36” x 48”
8. HR5656                   48” x 48”
9. HR3862                   30” x 54”
10. HR32104               24” x 96”
11. HR38104               30” x 96”
12. HR44104               36” x 96”
13. G2436                   24” to 36” Gate

PART 3 – EXECUTION:
3.01 PREPARATION:
A. Verify that substrate is smooth and clean to extent needed to receive work.
B. Review approved shop drawings for locations of hatch rail system.
C. Paint and or repair all mechanical hatch parts and flashings as needed or required.
D. Make any roof related repairs or replacement to base flashing before installing new guard-rail system, use only materials recommended by the roofing manufacturer.

3.02 INSTALLATION:
A. Field customize to fit existing condition or as specified herein.
B. Set curb framing gasket around roof opening under hatch counter flashing, tighten to fit opening.
C. Add the four comer posts into receiver and bolt to frame.
D. Install cross rails into preset clamps and adjust with wrench.
E. Add chain or gate as specified by manufacturer.
F. Tighten all nuts bolts and allen screws.